Construction of a new production building at Sayama Technical Center
09/12/2021
TOA-DKK Corporation (Head office: Shinjuku Ward, Tokyo, Representative board member: Toshio Takahashi) decided to construct a new production building within the Sayama Technical Center in Sayama City, Saitama Prefecture, as a production base responsible for the mother function.
Construction of a New Production Building at Sayama Technical Center
Purpose and background of construction of new production building.
Under our current medium-term management plan (fiscal 2019 to fiscal 2021), we have been promoting the maintenance and succession of core technologies and efforts for new technologies with the aim of returning to production under the slogan "Advanced Manufacturing." Under the new medium-term management plan (fiscal 2022 to fiscal 2024), we will further collaborate with the development, production engineering, and manufacturing divisions to strengthen quality and price competitiveness and expand production by improving production efficiency through DX.
Therefore, we will renovate the aged buildings that has been around for more than 50 years at the Sayama Technical Center, and construct a new production building adjacent to the Development Technology Center, thereby establishing a mother factory function that enables the speed from the development of new products to mass production. In addition, the new production building will be transferred and integrated with the design and manufacturing function of the applied analytical analyzer, which will be carried out by the Tokyo Engineering Center (Higahshiyamato City, Tokyo), another production base in the metropolitan area, to accelerate the supply of products in accordance with customer needs. Furthermore, as a highly functional logistics base, we will strengthen our system for immediate delivery of productions and parts that respond to after-sales service and e-commerce.
The new production building aims at net-zero energy buildings (ZEBs) for the realization of a decarbonization community.
Overview of the new production building
Address | : | 613 Kita Iriso, Sayama City, Saitama Prefecture | ||||
Building Outline | : | Total floor area; approx. 8200 m2, 4 floors, Steel | ||||
Application | : | Multi-purpose/new production lines, test facilities,BCP | ||||
Construction Plan | : | March 2022/ February 2024 (planned) | ||||
Budget | : | Approx. 2.7 billion yen | ||||
Purpose | : | Energy conservation/creation through photovoltaic power, creation of ZEB |